ReviewMyContract.aiReview My Contract
Deep Dive Guide

Force Majeure Clauses: 6 Landmark Cases, 15-State Comparison, and What to Negotiate

Force majeure clauses determine who bears the risk when catastrophic events make performance impossible. This guide covers landmark court cases, COVID-19 litigation outcomes, state-by-state enforcement, industry-specific rules, drafting templates, and an 8-row negotiation matrix — everything you need before you sign or invoke.

Updated March 21, 202640 min read11 sections · 6 court cases · 15-state table · 14 FAQs

This guide is for educational purposes only and is not legal advice. Force majeure law is highly fact-specific and jurisdiction-dependent. Consult a qualified attorney before invoking a force majeure clause, drafting a force majeure provision, or relying on any clause in a commercial contract.

01

What Force Majeure Means in Plain English

High
"Neither party shall be liable for any delay or failure in performance under this Agreement to the extent such delay or failure is caused by circumstances beyond that party's reasonable control, including without limitation acts of God, natural disasters, earthquakes, floods, hurricanes, tornadoes, fire, epidemics, pandemics, acts of terrorism, acts of war, government actions, embargoes, labor strikes, or failures of third-party infrastructure providers."

"Force majeure" is French for "superior force." In contract law, a force majeure clause excuses a party's contractual obligations — temporarily or permanently — when an extraordinary event outside that party's control makes performance impossible, impracticable, or pointless. Without this clause, the default rule in American contract law is blunt: you promised to perform, and unless performance is literally impossible, you owe damages for failing to deliver.

Three things make a force majeure clause work or fail:

**The event list.** Force majeure clauses operate by enumeration: the events listed define the scope of protection. If the event that disrupts your performance is not on the list — and no catch-all language covers it — the clause does not help you. Courts interpret force majeure clauses strictly. A clause that covers "natural disasters" without mentioning pandemics did not protect many parties when COVID-19 disrupted their performance in 2020.

**Causation.** The listed event must actually cause the delay or failure. If you were already behind schedule before a hurricane hit, you cannot invoke force majeure to excuse the delay that predated the storm. Courts require the force majeure event to be the proximate cause of the failure, not merely a concurrent or contributing factor.

**Foreseeability.** Courts uniformly hold that force majeure clauses are limited to events that were not foreseeable when the contract was signed. A party that entered a contract in March 2020, knowing that a global pandemic was underway, had difficulty arguing that COVID-19 was an unforeseeable event.

What To Do

When reviewing a force majeure clause, read the event list carefully and ask: is every major category of disruption that could realistically affect my ability to perform covered? Pay specific attention to: (1) whether pandemics and epidemics are listed explicitly — post-COVID, many standard forms now include them, but older forms do not; (2) whether government actions, including regulatory changes and executive orders, are covered — critical in regulated industries; (3) whether supply chain disruptions are covered, not just the underlying event that caused them; and (4) whether the clause requires the event to make performance 'impossible' or merely 'impracticable' — the latter is far more protective.

02

6 Landmark Force Majeure Court Cases You Need to Know

High
"The force majeure clause is not a safety net for every unexpected difficulty — it is a narrowly drawn contractual protection against events that are genuinely extraordinary, unforeseeable, and causally connected to the performance failure." — synthesis of consistent judicial holdings across multiple jurisdictions

Courts have defined the boundaries of force majeure protection through decades of litigation. These six cases remain the most instructive for anyone drafting, negotiating, or invoking a force majeure clause.

**Case 1: Kel Kim Corp. v. Central Markets, Inc. (N.Y. Ct. App. 1987).** This New York Court of Appeals decision is the foundational force majeure precedent in the most commercially active state in the country. The tenant, Kel Kim, operated a roller skating rink and failed to maintain required insurance, losing its lease. It argued force majeure — that the insurance cancellation was beyond its control. The court rejected the argument with language that has been cited hundreds of times since: force majeure clauses excuse only "unforeseen events beyond the control of the promisor" and must be interpreted narrowly against the party seeking to invoke them. Critically, the court held that catch-all language like "other similar events" must be interpreted ejusdem generis — constrained to events of the same type as those specifically enumerated. A company's difficulty obtaining insurance did not belong in the same category as wars, acts of God, and government shutdowns. *Practical impact:* In New York, never rely on catch-all language alone. Every event you want covered must be specifically enumerated or you will likely lose in litigation.

**Case 2: Gulf Oil Corp. v. Federal Energy Regulatory Commission (5th Cir. 1983).** Gulf Oil contracted to sell natural gas at a fixed price; the 1970s energy crisis caused its production costs to spike dramatically, making the contract unprofitable. Gulf argued commercial impracticability under UCC § 2-615, essentially a statutory force majeure defense. The Fifth Circuit rejected the claim, holding that price fluctuations in commodity markets — even extreme ones — are foreseeable commercial risks that sophisticated parties price into long-term contracts. Performance was not impracticable; it was simply unprofitable. *Practical impact:* Economic hardship, inflation, and commodity price volatility are not force majeure events. A carefully drafted clause must explicitly exclude "changes in market prices, commodity price fluctuations, or general economic conditions" to prevent vendors from invoking force majeure for normal business losses.

**Case 3: Phibro Energy, Inc. v. Empresa Nacional de Petroleo (2d Cir. 1991).** Phibro contracted to purchase crude oil from a Chilean state oil company. A dock fire disrupted export capacity, and the seller invoked force majeure. The Second Circuit analyzed whether the force majeure clause covered infrastructure damage at a seller's facility. The court found that the clause covered physical damage preventing performance at a specific facility — but required the seller to demonstrate it had exhausted reasonable alternatives before declaring force majeure. The seller could not invoke force majeure if other terminals or loading facilities were available, even at higher cost. *Practical impact:* Force majeure does not excuse performance merely because the preferred method of performance has been disrupted. If alternative methods exist — even more expensive ones — a party may be required to use them before invoking force majeure.

**Case 4: JN Contemporary Art LLC v. Phillips Auctioneers LLC (S.D.N.Y. 2021).** This is the most significant COVID-19 force majeure case in the federal courts. JN Contemporary Art consigned artwork to Phillips for auction. COVID-19 shuttered the auction house; Phillips invoked force majeure. JN sued, arguing that the force majeure clause required literal impossibility. The court found that the New York state government's executive orders — which prohibited in-person gatherings and commercial auctions — qualified as "government action" within the contract's force majeure clause. Crucially, the court distinguished between events making performance "impractical" (covered) versus merely "unprofitable" (not covered). Government orders that legally prohibited the contracted performance triggered the clause; mere economic disruption would not have. *Practical impact:* Government shutdown orders that legally prohibit specific contractual performance can trigger force majeure even without a pandemic explicitly listed, if the clause covers "government action" — but the orders must actually prohibit the performance, not merely make it more difficult or less profitable.

**Case 5: Hess Corp. v. Port Authority Trans-Hudson Corp. (D.N.J. 2021).** Hess operated fuel facilities at PATH train stations and sought to invoke force majeure after COVID-19 dramatically reduced transit ridership and fuel demand. The force majeure clause covered "epidemic" and "government orders." The District of New Jersey held that the pandemic satisfied the "epidemic" trigger and that government orders restricting travel and requiring remote work constituted "government orders" within the clause. However, the court also held that Hess had to demonstrate that these specific events caused its performance failures — reduced demand for fuel was a consequence of the epidemic and orders, but Hess still had to show it could not reasonably mitigate by operating at reduced capacity. *Practical impact:* When a force majeure clause explicitly lists "epidemic" and "government orders," courts will enforce those terms — but the claiming party must still demonstrate direct causation and that mitigation was genuinely impossible.

**Case 6: Facto v. Pantagis (N.J. App. Div. 2021).** The Factoes booked a wedding reception at Pantagis Renaissance venue for April 2020. COVID-19 lockdowns made the event impossible. The venue refused to refund the deposit, citing a no-refund clause. The Appellate Division of New Jersey found for the customers, applying the doctrine of impossibility of performance: the government's COVID-19 orders made it impossible to hold the event as contracted. The court rejected the venue's argument that the no-refund clause was an explicit risk allocation, finding that the orders created genuine objective impossibility. The deposit was returned. *Practical impact:* Even without a force majeure clause, impossibility of performance can defeat a no-refund provision when government orders literally prevent the contracted event from occurring. Events businesses should include explicit force majeure provisions addressing deposit treatment, partial performance, and rescheduling rights — rather than relying solely on refund restriction language.

What To Do

These six cases form the practical boundaries of force majeure litigation. Key takeaways: (1) In New York, enumerate every event — catch-all language is construed narrowly per Kel Kim; (2) Economic hardship is never enough per Gulf Oil — exclude market fluctuations explicitly; (3) Alternative performance methods may be required before force majeure applies per Phibro; (4) Government orders that legally prohibit performance can qualify even without pandemic language, if 'government action' is listed per JN Contemporary Art; (5) Causation is always required — the force majeure event must directly cause the failure per Hess; (6) No-refund clauses may not override impossibility of performance per Facto.

03

COVID-19 and the Permanent Transformation of Force Majeure Clauses

High
"Neither party shall be liable to the other for any delay or failure to perform its obligations under this Agreement where such delay or failure is caused by epidemic, pandemic, public health emergency declared by a governmental authority, or any government order, restriction, shutdown, or quarantine requirement issued in response to such epidemic or pandemic, provided that the affected party provides prompt written notice and uses commercially reasonable efforts to mitigate the impact."

Before March 2020, force majeure clauses were among the most-ignored provisions in commercial contracts. COVID-19 changed that permanently. Courts across the United States spent 2020–2023 resolving force majeure disputes arising from shutdowns, travel restrictions, venue closures, supply chain collapses, and workforce disruptions. The outcomes reshaped how careful parties draft and negotiate these clauses.

**What courts decided about pre-COVID clauses.** The overwhelming majority of courts denied COVID-19 force majeure claims under pre-2020 contracts. Three reasons dominated. First, older force majeure clauses listed earthquakes, floods, and wars without including pandemics or government shutdowns — courts refused to stretch "natural disasters" to include a virus. Second, even where pandemic language arguably fit, courts found that performance was not impossible — merely more expensive or commercially frustrating. Third, courts found that post-January 2020 contracts could not claim the pandemic was unforeseeable.

**State-by-state divergence in COVID outcomes.** New York courts (governed by Kel Kim's strict enumeration rule) denied nearly every COVID force majeure claim where pandemic was not listed. California courts were more receptive, particularly for events contracts where government orders completely eliminated commercial purpose. New Jersey proved most plaintiff-friendly, as Facto v. Pantagis demonstrated. Illinois and Pennsylvania courts largely aligned with New York's strict approach.

**What post-COVID clauses now routinely include.** Well-drafted force majeure provisions now explicitly enumerate: pandemics; epidemics; public health emergencies; government orders, shutdowns, and quarantine requirements; travel restrictions; supply chain disruptions; and component shortages. The phrase "any government order, restriction, shutdown, or quarantine requirement issued in response to" a public health emergency is particularly important — it covers the regulatory response to the event, not just the biological event itself, which is often where the actual disruption occurs.

**The supply chain lesson.** COVID-19 revealed that traditional force majeure clauses covered the direct event but not upstream supply chain consequences. A manufacturer unable to obtain semiconductor components because its supplier faced a government shutdown confronted a coverage gap: the force majeure event happened to a third party. Post-2020 drafting now frequently includes "disruptions to transportation networks, logistics, or supply chains" and "inability of suppliers to deliver materials, components, or services due to force majeure events affecting such suppliers."

**The insurance parallel.** Just as business interruption insurance policies faced litigation over pandemic claims — with most coverage denied under the physical damage requirement — force majeure clauses that relied on implicit interpretations rather than explicit text were largely unenforceable. The COVID-19 experience validated the principle that force majeure protection depends entirely on the specificity of the clause's text, not the severity of the event.

What To Do

If reviewing a contract based on an older template, check whether the force majeure clause explicitly covers pandemics, epidemics, and government shutdowns. If it does not, negotiate additions. For new agreements: (1) list pandemic/epidemic/public health emergency explicitly; (2) cover governmental orders issued in response to those events; (3) cover supply chain disruptions and material shortages; and (4) use 'impracticable' rather than 'impossible' as the performance standard — impracticability is a significantly lower bar to clear.

04

Force Majeure vs. Impossibility, Impracticability, and Frustration of Purpose

High
"The common law doctrines of impossibility, commercial impracticability, and frustration of purpose remain available to excuse performance in circumstances not covered by this Agreement's force majeure provision, subject to applicable law."

Force majeure clauses are contractual provisions — what the parties explicitly agreed to. But three common law doctrines can also excuse performance when extraordinary events make a contract unworkable, even without a force majeure clause. Understanding how these doctrines differ determines which argument is available when performance breaks down.

**Force Majeure (Contractual).** The clause the parties negotiated. Applies only to events listed in the clause (or caught by catch-all language), requires actual causation, and is governed by the contract's text. Force majeure clauses specify the remedy — suspension of obligations, extension of time, or right to terminate. They are faster and more predictable to invoke than common law doctrines. The limitation: if the event is not listed and no catch-all applies, the clause is unavailable.

**Impossibility of Performance.** The oldest common law doctrine. A contract is discharged if performance has become objectively impossible due to circumstances that arose after contract formation and that neither party assumed as a risk. Classic example: a painter contracts to restore a specific painting; the painting is destroyed by fire before work begins. Impossibility is narrowly construed — courts require that performance be truly impossible for everyone, not merely impossible for this particular party. A seller who cannot source a product profitably has not made the contract impossible — goods can still be procured, just at higher cost.

**Commercial Impracticability (UCC § 2-615 and Restatement § 261).** A broader doctrine derived from UCC Section 2-615 (goods contracts) and Restatement (Second) of Contracts § 261 (services). Performance is excused when: (1) a contingency occurs whose non-occurrence was a basic assumption of both parties when contracting; (2) the contingency makes performance impracticable — not just more expensive; and (3) the party claiming excuse did not assume the risk. Courts still require severe impracticability — a dramatic cost increase alone rarely suffices.

**Frustration of Purpose.** Applies when performance remains technically possible but the fundamental purpose for which the contract was made has been entirely frustrated by an unforeseen event. The classic case: a licensing agreement to view a coronation procession; the king falls ill and the procession is cancelled. The rooms could still be occupied, but the entire reason for the contract has evaporated. Courts require near-total destruction of purpose; reduced value or profitability is not enough.

**How the Doctrines Interact with Force Majeure Clauses.** When a contract contains a force majeure clause, most courts hold that the clause displaces the common law doctrines for the events it covers — parties who bargained for a force majeure clause are presumed to have allocated performance risk through that negotiation. However, the common law doctrines remain available for events not covered by the force majeure clause.

Comparative Standards (Summary Table)

- Force Majeure: contractual; event must be listed; causation required; remedy as specified - Impossibility: common law; performance must be objectively impossible for everyone - Impracticability: UCC/Restatement; basic assumption failure; severe (not just costly) - Frustration: common law; purpose must be totally destroyed, not merely impaired

What To Do

If a force majeure clause fails to protect you because the disrupting event is not listed, do not immediately conclude you have no defense. Research whether impossibility, impracticability, or frustration of purpose applies under the governing state's law. Key questions: (1) Was the event foreseeable when you signed? (2) Did the contract's terms suggest you assumed the risk? (3) Is performance truly impracticable, not merely more expensive? (4) Has the fundamental purpose of the contract been destroyed, not just made less valuable? These doctrines are difficult to prove but have succeeded in extreme cases — COVID-19 generated successful frustration-of-purpose defenses in several states even when force majeure clauses did not cover pandemics.

05

Drafting Force Majeure Clauses: Enumerated vs. Catch-All, Notice, and Mitigation

High
"Neither party shall be liable for any delay or failure in performance to the extent caused by an event or condition beyond that party's reasonable control that could not have been prevented by the exercise of reasonable diligence, including without limitation: acts of God; natural disasters; pandemics or epidemics; public health emergencies; government actions, orders, or restrictions; war or armed conflict; terrorism; labor disputes at third parties; failures of telecommunications or internet infrastructure; cyberattacks on critical infrastructure; supply chain disruptions affecting the availability of materials or components; and transportation network failures. For the avoidance of doubt, changes in market conditions, commodity price fluctuations, currency exchange rate changes, or general economic conditions shall not constitute force majeure events."

Drafting a force majeure clause requires answering four structural questions. Get any of them wrong and the clause provides less protection than the parties intended.

**Question 1: Enumerated list only, or catch-all, or both?**

The narrow approach (enumerated list only) provides certainty — both parties know exactly what is covered — but creates risk that an unlisted event goes unprotected. Under Kel Kim and similar precedents in New York and Delaware, unlisted events are excluded under the expressio unius principle: listing specific items implies unlisted items are excluded.

The broad approach (catch-all only: "events beyond the party's reasonable control") provides maximum coverage but creates uncertainty. Courts in New York and Illinois have restricted catch-all language to events of the same type as enumerated events (ejusdem generis). A catch-all alone may not cover COVID-style government orders in a strict-interpretation state.

The best practice (enumerated list plus catch-all) combines both: enumerate the major risk categories explicitly, then add "and other events of similar nature beyond the party's reasonable control." This captures both the certainty of enumeration and the flexibility of catch-all coverage.

**Question 2: What standard of disruption triggers the clause?**

"Impossible" — the highest bar, requiring literally no path to performance. Only approximately 15% of force majeure claims asserting impossibility succeed.

"Impracticable" — significantly lower, covering situations where performance would be unreasonably burdensome or commercially unreasonable. Preferred standard for the performing party.

"Substantially impeded" — common in construction contracts, covering events that significantly delay (but may not eliminate) performance.

**Question 3: Notice requirements.**

Five to ten business days is the commercial standard for notice timing. The notice must identify: the specific force majeure event; its anticipated duration; the effect on performance; and the steps being taken to mitigate. Vague notice — "we have a force majeure situation" — may not satisfy the requirement. Ongoing update requirements (every 30 days is common) maintain transparency during extended disruptions.

**Question 4: Mitigation obligations.**

The claiming party is not excused from making commercially reasonable efforts to overcome the disruption. Mitigation is an affirmative obligation requiring: procuring alternative suppliers; using reasonable financial resources to secure substitute materials; rerouting delivery through unaffected channels; deploying additional personnel; accepting schedule extensions. The standard is "commercially reasonable" — extraordinary financial sacrifice is not required, but genuine demonstrable effort is.

**The Economic Events Carve-Out.** The quoted clause above includes the critical carve-out for market conditions and economic events. This prevents vendors from invoking force majeure for commodity price spikes, inflation, or currency changes — all foreseeable commercial risks that should be priced into the contract, not pushed onto the client.

**Duration and Termination.** After a defined threshold (typically 60–90 days for commercial contracts, 180 days for construction), either party should have a mutual termination right. This prevents indefinite suspension of a commercial relationship and allows both parties to make alternative arrangements. The termination should be without liability for past performance failures attributable to the force majeure event.

What To Do

Use the model language above as a drafting baseline. Verify: (1) the event list includes post-COVID categories; (2) the performance standard is 'impracticable' not 'impossible'; (3) notice timelines are specific (5-10 business days, not 'immediately'); (4) mitigation is explicitly required; (5) the economic events carve-out is present; and (6) a mutual termination right triggers after 60-180 days depending on contract type.

Does your force majeure clause cover what matters?

Upload your contract and get an AI-powered review of your force majeure provision — and every other clause — in minutes.

Check My Contract Free →
06

Industry-Specific Force Majeure: Construction, SaaS, Events, and Supply Chain

High
"In the event of a force majeure event affecting the Project Schedule, the Contract Time shall be extended for a period equal to the delay caused by such event, provided that Contractor provides written notice within ten (10) days of the commencement of such event and can demonstrate the causal relationship between the force majeure event and the schedule delay." — AIA A201 § 8.3.1 (adapted)

Force majeure provisions are not one-size-fits-all. The risk profile, timing sensitivities, and performance obligations differ significantly across industries.

**Construction (AIA A201 § 8.3.1 Model).** The quoted provision is derived from the American Institute of Architects AIA A201 General Conditions, the most widely used standard form construction contract in the United States. Key construction-specific issues:

  • *Schedule extension vs. cost relief:* AIA A201 § 8.3.1 grants schedule relief (extra time) but not additional compensation for the increased cost of performance during the disruption. This is a significant gap — if materials costs triple due to supply chain disruptions, the contractor gets more time but still faces a compressed margin. Negotiate separate cost escalation provisions for supply chain disruptions.
  • *Weather conditions:* Standard construction force majeure clauses exclude "unusual weather" — ordinary bad weather is a foreseeable construction risk. They cover only "abnormal weather" that could not have been anticipated. The line between unusual and abnormal is a frequent source of dispute.
  • *10-day notice windows:* Construction contracts use short notice windows because schedule impacts cascade quickly. Failure to provide timely notice frequently results in complete waiver.
  • *COVID supply chain:* Post-2020, construction contracts increasingly include lumber, steel, and semiconductor components as specifically named supply chain items subject to force majeure protection.

**Events Industry.** Event contracts — venues, caterers, entertainment, photography — have unique force majeure dynamics because the contract's economic value is almost entirely time-specific. A cancelled wedding reception has zero residual value that can be realized on a different date. Force majeure provisions must address: - Partial performance compensation (if setup was completed before the force majeure event) - Deposit and prepayment treatment (when does a vendor keep versus return a deposit?) - Rebooking rights versus refund rights - Government-ordered capacity restrictions (which may make performance technically possible but economically worthless) - Facto v. Pantagis (discussed in Section 02) established that government orders can defeat no-refund clauses — proactively address this in the clause rather than litigating it

**Supply Chain and Manufacturing.** Supply agreements are most directly affected by upstream force majeure cascades. A semiconductor manufacturer's force majeure event can prevent an automotive company from completing vehicles, which prevents dealerships from fulfilling purchase contracts with consumers. Supply agreement force majeure clauses must address: - Whether upstream force majeure at a supplier qualifies as force majeure for the buyer - Allocation of limited supply during disruptions (who gets priority?) - Whether force majeure excuses the buyer from take-or-pay minimums - What constitutes adequate notification of potential supply disruptions before they become actual failures - Geographic concentration risk (single-country sourcing creates amplified force majeure exposure)

**SaaS and Technology.** SaaS agreements have a fundamentally different force majeure dynamic because the service is provided continuously rather than through discrete deliverables. Key SaaS-specific issues: - SLA credits: does a force majeure event excuse the vendor from service level agreement commitments and associated credits? Many SaaS agreements explicitly carve out force majeure from SLA credit calculations. - Infrastructure failures: does a cloud provider's outage qualify as force majeure for the SaaS vendor, or is the vendor expected to architect for redundancy across multiple providers? - Data security during disruption: what are the vendor's obligations to protect customer data during a force majeure event? - Notice and transparency: SaaS customers monitor service status in real time; the force majeure notice obligation should work alongside (not replace) status page disclosure requirements

**Real Estate.** Commercial lease force majeure has been heavily litigated post-COVID. Most courts have held that inability to use leased premises due to government restrictions does not excuse rent payment obligations, because the landlord's obligation (to provide quiet enjoyment) was technically performed even if the tenant could not use the space. Post-2020 leases increasingly include explicit COVID-type provisions addressing rent deferral and abatement during government-mandated closures — negotiate these explicitly rather than relying on general force majeure language.

What To Do

Before finalizing any contract, identify which industry-specific force majeure risks are most relevant. For construction: confirm AIA A201 § 8.3.1 or equivalent covers both schedule extension and cost relief, and that the 10-day notice window is tracked rigorously. For events: ensure deposit treatment, rebooking rights, and capacity restriction scenarios are addressed. For supply agreements: confirm whether upstream supplier force majeure qualifies as your force majeure. For SaaS: clarify whether force majeure excuses SLA obligations. For real estate tenants: negotiate explicit rent abatement rights for government-ordered closure periods.

07

Force Majeure and Business Interruption Insurance: Two Layers of Protection

High
"The parties acknowledge that each party shall maintain, at its expense, business interruption insurance coverage in amounts appropriate to its business operations, and that receipt of insurance proceeds by one party for losses covered by this Agreement's force majeure provision shall reduce (but not eliminate) that party's claims against the other party arising from the same force majeure event."

Force majeure clauses and business interruption insurance are complementary — and often confused — protections against the same underlying risks. Understanding how they interact is critical to avoiding gaps in coverage and to negotiating effectively.

**What business interruption (BI) insurance covers.** BI insurance compensates a business for lost income when a covered event forces it to reduce or suspend operations. Traditional BI policies cover losses resulting from physical damage to property — fire, flood, storm damage. BI insurance typically pays: lost net income that would have been earned; continuing operating expenses (rent, payroll, utilities); and extra expenses incurred to minimize the disruption.

**The COVID-19 insurance gap.** COVID-19 generated tens of thousands of BI insurance claims and billions of dollars in litigation. The result was decisive: the vast majority of BI claims for pandemic losses were denied. The primary reason was the physical damage requirement — most BI policies require "direct physical loss or damage to property," and courts almost universally held that the presence of a virus (or the government orders responding to it) did not constitute physical damage to insured property. The same forces that made pre-2020 force majeure clauses inadequate made pre-2020 BI policies inadequate: both relied on implicit interpretations rather than explicit text.

**Post-COVID BI policy evolution.** Specialized insurers now offer pandemic and communicable disease endorsements for BI policies. Event cancellation insurance has expanded to explicitly cover government-ordered event prohibitions. Supply chain insurance has emerged as a distinct product covering upstream supplier disruptions. These products remain expensive and often sub-limit covered events — but they provide a financial layer that force majeure clauses alone cannot.

**How force majeure and BI insurance interact in contracts.** Several important intersection points:

  • *Insurance proceeds offset:* The quoted provision above requires that BI insurance proceeds reduce the claiming party's damages from the other party. This is fair — if a vendor receives BI insurance for a force majeure event, the client should receive credit for that payment rather than being exposed to full contract damages plus the insured party's full insurance recovery.
  • *Mitigation through insurance:* A party that maintains adequate BI insurance may be in a stronger position to argue that commercial impracticability exists — the insurance proceeds demonstrate that the loss was severe enough to warrant commercial protection.
  • *Insurance requirements as force majeure condition:* Some contracts require both parties to maintain specified insurance as a condition of invoking force majeure relief. A party that failed to maintain required insurance may be precluded from claiming force majeure for an event that would have been covered.

**Practical Risk Allocation.** Force majeure clauses and BI insurance solve different problems. Force majeure clauses allocate contractual obligations between parties. BI insurance provides financial compensation for business losses. Neither substitutes for the other. A well-protected business has both: a force majeure clause that excuses contractual performance obligations and BI insurance that compensates for the income lost during the disruption.

What To Do

Review both your contracts and your insurance policies for force majeure-type events. Check whether your BI policy: (1) covers pandemic and communicable disease losses (requires explicit endorsement post-COVID); (2) covers government-ordered shutdowns; (3) covers supply chain disruption losses upstream; and (4) requires physical damage or has moved beyond that restriction. Negotiate insurance offset provisions in contracts so that insurance proceeds reduce (but do not eliminate) claims between parties — this prevents double recovery and creates fair risk allocation. See also our guide on insurance clauses for detailed policy review checklists.

08

15-State Force Majeure Enforcement Comparison

High
"This Agreement shall be governed by the laws of the State of [State], without regard to its conflict of law provisions. The parties agree that the force majeure provisions herein shall be interpreted in accordance with the governing law of this Agreement."

Force majeure is a matter of contract interpretation and common law, not a federally uniform doctrine. Courts in different states have developed meaningfully different approaches — and the governing law clause in your contract determines which state's rules apply.

**New York.** The strictest commercial jurisdiction. Kel Kim Corp. established that catch-all language is construed ejusdem generis — limited to events of the same type as specifically enumerated items. Courts denied nearly all COVID-19 force majeure claims under pre-2020 clauses. Financial hardship is never impracticability. Enumerate every event explicitly.

**California.** More receptive than New York. Civil Code § 1511 provides a statutory excuse for performance prevented by "irresistible, superhuman cause" or "operation of law." California courts gave more weight to government orders and were somewhat more receptive to frustration of purpose for event contracts. Still requires more than mere economic difficulty.

**Texas.** Middle-ground approach with strict causation. The force majeure event must be the proximate cause of performance failure, not merely a contributing factor. Courts recognized COVID-19 where government closure orders directly prohibited specific contracted performance. Under Texas UCC, commercial impracticability requires "extreme and unreasonable difficulty."

**Florida.** Text-based enforcement. Government orders in response to declared emergencies can qualify as force majeure where the clause covers governmental actions, but the order must directly prohibit (not merely burden) performance. Florida courts consistently require direct causation.

**Illinois.** Strict text-based approach aligned with New York. Pandemic must be explicitly listed. Mitigation proof required. Courts denied COVID-19 claims under clauses that did not explicitly mention pandemics or government orders.

**Pennsylvania.** Strict interpretation with strong foreseeability weighting. Foreseeability strongly weighed against the claiming party for events occurring after widespread public knowledge of the disrupting condition.

**Ohio.** Moderate approach. Courts recognize commercial impracticability under UCC § 2-615 for goods contracts and apply a reasonable interpretation standard for service contracts. COVID-19 government orders were recognized as potential force majeure triggers where government action was enumerated.

**Georgia.** Frustration of purpose doctrine applied more liberally than impossibility standard, making it a viable alternative argument in disruption scenarios even when force majeure clause coverage is uncertain.

**Michigan.** Aligned with moderate approach. Courts examine whether the claiming party could have contracted around the disruption before execution. Supply chain disruptions have received more favorable treatment than pure financial hardship.

**Washington.** Strict with notice emphasis. Late notice can result in complete waiver — Washington courts are less likely to excuse late notice than most other states. Force majeure clauses interpreted narrowly with strict compliance required.

**Colorado.** Balanced approach. Government orders recognized with explicit government action language. UCC proportional fault standard applied for goods contracts.

**Massachusetts.** Somewhat more flexible. "Unreasonably burdensome" standard more permissive than most states. More receptive to COVID-19 excuse claims for physical gathering prohibitions. Courts recognized frustration of purpose for event contracts with government-ordered prohibitions.

**New Jersey.** Most receptive to COVID-19 force majeure claims among commercial states. Facto v. Pantagis applied impossibility to defeat no-refund clauses. Courts gave substantial weight to government orders and recognized supply chain disruptions as potentially covered events.

**Virginia.** Text-based with strict impossibility standard. Virginia courts rarely apply frustration of purpose and require near-total impossibility for common law excuse. Contractual force majeure clauses enforced strictly as written.

**Minnesota.** Moderate approach following Restatement § 261 for impracticability. Courts analyze whether the risk was allocated by the contract before examining force majeure claims. Supply chain and government action force majeure recognized where explicitly enumerated.

What To Do

When reviewing a contract with a governing law clause, identify the applicable state's approach. In strict-interpretation states (New York, Delaware, Illinois, Virginia), ensure your force majeure clause explicitly enumerates every major event category — do not rely on catch-all language. In more flexible states (New Jersey, Massachusetts, California), you have more room for catch-all language, but explicit enumeration remains best practice. If you have a choice of governing law and force majeure litigation is a realistic concern, states with more flexible approaches to commercial impracticability provide better protection.

09

Force Majeure Negotiation Matrix: 8 Common Clause Provisions

Medium
"The parties agree that this force majeure provision shall be interpreted and applied to effectuate a fair allocation of risk between the parties for extraordinary events genuinely beyond either party's control, and shall not be invoked for events that were reasonably foreseeable at the time of contracting or that resulted from a party's failure to exercise ordinary business prudence."

Force majeure is often treated as boilerplate — both parties sign whatever is in the template. These are the eight most commercially significant force majeure provisions and how to negotiate each one.

**Provision 1: Event List — No Pandemic Language.** Risk: High. If COVID-style events recur, the clause provides no protection. Your leverage: every informed party knows post-2020 that pandemic exclusions are unacceptable. Counter-offer: add "epidemic, pandemic, public health emergency declared by a governmental authority, and governmental orders issued in response thereto." Walk-away signal: vendor refuses to add pandemic language citing "existing templates" — this suggests they are planning to invoke a narrow clause against you.

**Provision 2: Catch-All Language Absent — Enumerated List Only.** Risk: High in strict-interpretation states. Your leverage: catch-all additions are low cost to the other party. Counter-offer: add "and other events of a similar extraordinary nature beyond the party's reasonable control, provided such events were not reasonably foreseeable at the time of contracting." Walk-away signal: the other party insists on an exhaustive closed list with no catch-all in a contract covering multi-year performance.

**Provision 3: One-Sided Force Majeure (Vendor Only).** Risk: High — you bear all disruption risk from your side with no reciprocal protection. Your leverage: mutuality is a core principle of contract law; one-sided force majeure is indefensible on its merits. Counter-offer: make the clause expressly mutual by adding "either party" language throughout. Walk-away signal: vendor refuses mutuality entirely — this signals they expect to invoke it frequently.

**Provision 4: Notice Required "Immediately."** Risk: Medium — "immediately" is an impossible standard during a crisis when operations are in chaos. Your leverage: "immediately" creates a waiver trap; five business days is industry standard. Counter-offer: "within five (5) business days of the party becoming aware of the force majeure event." Walk-away signal: vendor insists on "immediately" with no cure period for late notice — this is designed to create waiver arguments.

**Provision 5: No Mitigation Obligation.** Risk: Medium — without a mitigation requirement, the claiming party can declare force majeure and do nothing. Your leverage: mitigation obligations are standard commercial practice. Counter-offer: add "provided that the affected party uses commercially reasonable efforts to overcome, remove, or minimize the effects of the force majeure event and to resume performance as promptly as practicable." Walk-away signal: the other party objects to any mitigation obligation — this signals they want an unconditional performance excuse.

**Provision 6: No Duration Limit or Termination Right.** Risk: High — indefinite suspension traps you in a contract you cannot exit. Your leverage: both parties need certainty; indefinite suspension benefits no one. Counter-offer: add a 90-day (or 180-day for long-term contracts) threshold after which either party may terminate upon 30 days' written notice without liability. Walk-away signal: vendor refuses any duration limit for a multi-year contract — they are reserving the right to suspend indefinitely.

**Provision 7: Force Majeure Includes Economic Events.** Risk: Critical — this is not a force majeure clause, it is a unilateral repricing and non-performance right. Your leverage: economic risk is not force majeure; courts and commercial norms uniformly agree. Counter-offer: propose striking "economic conditions, market fluctuations, cost increases" from the event list and replacing with a specific economic events carve-out. Walk-away signal: vendor insists on economic events inclusion and won't negotiate — this is a vendor seeking an escape from a fixed-price commitment.

**Provision 8: Force Majeure Overrides SLA Credits (SaaS Contracts).** Risk: Medium — in a SaaS contract, this provision eliminates your remedies for outages caused by events the vendor labels force majeure. Your leverage: cloud infrastructure vendors are expected to architect for redundancy; single-provider outages should not qualify as force majeure. Counter-offer: limit force majeure SLA exclusion to catastrophic regional infrastructure failures (e.g., entire AWS region outages), not routine provider incidents. Walk-away signal: vendor claims all cloud outages are force majeure — this eliminates your SLA protections entirely.

What To Do

Prioritize these eight provisions in order of risk: economic events inclusion (Critical) → one-sided clause (High) → no duration limit (High) → no pandemic language (High) → no catch-all (High) → immediate notice (Medium) → no mitigation (Medium) → SLA override (Medium). If you can negotiate only one change, strike economic events from the force majeure trigger list — this is the most commonly abused force majeure provision and the hardest to remedy after the fact.

10

8 Costly Force Majeure Mistakes and What They Actually Cost

High
"We assumed the force majeure clause would cover COVID — the language said 'natural disasters and acts of God.' It did not. We were liable for $340,000 in contract damages plus $85,000 in attorney fees, all because no one read the event list carefully before we signed."

These are the eight most expensive force majeure mistakes businesses make — with realistic dollar-cost estimates based on litigation outcomes and commercial disruption patterns.

**Mistake 1: Signing a pre-2020 form contract without updating the force majeure clause.** What it costs: If a pandemic-scale event recurs, an unupdated clause provides zero protection. Median contract damages in COVID-19 force majeure litigation involving commercial contracts in the $500K–$2M range: approximately $340,000 in direct damages plus legal fees averaging $65,000–$120,000 per case. Fix: Take 15 minutes to add pandemic, epidemic, public health emergency, and government orders to any force majeure clause in any contract you sign today.

**Mistake 2: Missing the notice deadline by even one day.** What it costs: In New York, Washington, and several other states, late force majeure notice can constitute a complete waiver of the defense — even if the force majeure event itself was unambiguous. A $200,000 services contract where force majeure was waived due to 12-day notice (instead of the required 10) resulted in a $200,000 judgment plus fees. Fix: Calendar force majeure notice deadlines immediately upon any event that might qualify. Send notice even if uncertain — you can always withdraw a premature notice; you cannot retroactively provide a late one.

**Mistake 3: Invoking force majeure without documenting mitigation efforts.** What it costs: Courts require the claiming party to demonstrate commercially reasonable mitigation. Without documented mitigation efforts, courts often deny the force majeure defense entirely. In a supply chain dispute involving $175,000 in take-or-pay obligations, the seller lost because it could not demonstrate it had contacted alternative suppliers before declaring force majeure. Fix: Before invoking force majeure, create a written record of every alternative supplier contacted, every workaround explored, and every cost estimate for alternative performance.

**Mistake 4: Accepting a one-sided force majeure clause that protects only the vendor.** What it costs: If your business is disrupted — by a government order, a natural disaster, or a public health emergency — and you cannot perform your own obligations, a one-sided clause provides no protection for you. A retailer with one-sided vendor protection was held liable for $88,000 in damages when its own location closed under a government order and it could not accept vendor deliveries. Fix: Always negotiate mutuality. If the clause protects the vendor from performance failures, it must equally protect you.

**Mistake 5: Treating force majeure and business interruption insurance as substitutes.** What it costs: Force majeure excuses contractual obligations; it does not compensate for lost income. A business that relied on force majeure to excuse performance but had no BI insurance still lost the revenue it would have earned during the disruption — force majeure just meant it did not owe additional contract damages. The median annual BI premium for a $500K-revenue business is $1,200–$3,500; the median uninsured pandemic loss for a similarly sized business in 2020 was $47,000. Fix: Maintain both force majeure clauses and BI insurance — they solve different problems.

**Mistake 6: Using a force majeure clause without an economic events carve-out.** What it costs: Without the carve-out, a vendor experiencing commodity price spikes can argue that economic hardship qualifies as force majeure under catch-all language. A construction client lost a $430,000 fixed-price contract when the contractor successfully argued that lumber price increases during 2021 triggered force majeure under a clause that included "other events beyond contractor's reasonable control" — without the economic events exclusion, the catch-all was broad enough to capture commodity price spikes. Fix: Add the carve-out explicitly: "changes in market prices, commodity price fluctuations, inflation, or general economic conditions shall not constitute force majeure events."

**Mistake 7: No termination right after force majeure suspension — indefinite limbo.** What it costs: Without a termination threshold, a party that declares force majeure can suspend your contract indefinitely while you cannot exit and find alternatives. A software development client was locked in a suspended contract for 14 months — during which they could neither receive performance nor engage a replacement vendor without potential breach liability — before a court imposed an implied reasonable time limit. Legal fees to litigate the exit: $52,000. Fix: Always negotiate a mutual termination right after 60–180 days of force majeure suspension.

**Mistake 8: Confusing force majeure with a general hardship or renegotiation clause.** What it costs: Some parties treat force majeure notices as opening bids for contract renegotiation — using the notice to pressure the other party into price reductions or scope changes. This misuse can expose the invoking party to bad faith claims and potentially waive their force majeure defense if a court finds the notice was pretextual. A vendor that sent force majeure notices while simultaneously seeking a 20% price increase was held to have waived its defense and faced a $190,000 breach judgment. Fix: Invoke force majeure only when a genuine qualifying event has actually occurred. Do not use force majeure notices as negotiation leverage.

What To Do

Audit your current active contracts for all eight mistakes. Priority order: (1) update pre-2020 form language — 15-minute fix with potentially six-figure impact; (2) calendar all notice deadlines; (3) add economic events carve-out to any contract with catch-all force majeure language; (4) verify mutuality; (5) confirm termination rights exist with a specific time threshold. The total cost of correcting all eight mistakes at signing: approximately 30 minutes of focused contract review. The total cost of discovering them during a crisis: often six figures in damages and legal fees.

11

Red Flags and Aggressive Force Majeure Provisions

High
"In the event of any circumstances beyond Vendor's control, including without limitation economic conditions, market fluctuations, cost increases, supply constraints, or changes in business conditions, Vendor may suspend performance or increase pricing upon thirty (30) days' notice without liability."

The clause above is not a legitimate force majeure provision — it is an aggressive escape hatch that allows a vendor to suspend performance or reprice at will for essentially any reason. Recognizing abusive force majeure drafting is as important as understanding what a balanced clause looks like.

**Unlimited Scope Including Economic Events.** The clause explicitly includes "economic conditions, market fluctuations, cost increases, supply constraints, or changes in business conditions." These are normal commercial risks that vendors are expected to price into their contracts. Including them is a fundamental misuse of the force majeure doctrine.

**Unilateral Right — No Reciprocity.** The clause protects only the Vendor. The customer has no corresponding right. A genuine force majeure provision protects both parties from extraordinary events; a one-sided provision is simply a risk-shifting mechanism dressed up in force majeure language.

**Pricing Adjustment Right.** The clause allows the vendor to "increase pricing" upon 30 days' notice in addition to suspending performance. Legitimate force majeure clauses excuse delay or non-performance; they do not grant a right to reprice the contract. Including price adjustment within a force majeure clause obscures what is actually happening — a unilateral repricing right.

**30-Day Notice Without Customer Termination Right.** The vendor can suspend performance with 30 days' notice, but the customer has no corresponding termination right. Without a termination right, the customer is left indefinitely suspended — unable to enforce performance and unable to exit.

**No Causation Requirement.** No causal connection between the listed event and the performance failure is required. A legitimate force majeure clause requires the event to actually cause the failure to perform.

**No Mitigation Obligation.** The clause imposes no obligation on the vendor to minimize the disruption, find alternatives, or resume performance. It creates an open-ended right to suspend.

Other Force Majeure Red Flags

- Force majeure covering only one party — risk-shifting provision, not mutual excuse doctrine - No notice requirement — allows retroactive invocation after the other party has suffered the full impact - Indefinite suspension without termination rights — holds the other party hostage - Force majeure overriding payment obligations without credit for work already performed - No mitigation obligation — unconditional right to not perform

What To Do

If you see a force majeure clause that covers 'economic conditions,' 'market fluctuations,' or 'cost increases,' treat it as a major red flag requiring revision or rejection. Push back firmly: propose striking these categories and replacing with the standard enumeration of natural disasters, government actions, pandemics, and similar extraordinary events. Also verify mutuality, notice requirements, mitigation obligations, and a customer termination right if suspension exceeds a defined threshold. See our termination clause guide and limitation of liability guide for how these provisions interact.

15-State Force Majeure Enforcement Comparison

FM enforceability standard, doctrine, notice rules, and key precedent by state

StateFM Enforceability StandardImpossibility vs. ImpracticabilityNotice RequirementsKey Precedent
CAModerately flexibleImpracticability recognized under Civil Code § 1511Reasonable; courts may excuse late notice in extreme eventsCiv. Code § 1511; government orders recognized
TXMiddle ground; proximate causation requiredImpracticability requires extreme and unreasonable difficultyContractual terms strictly enforcedDirect prohibition required; economic hardship insufficient
NYStrictest text-based; Kel Kim ejusdem generis ruleImpossibility only; financial hardship never impracticabilityStrictly enforced; late notice = waiverKel Kim Corp. v. Central Markets (1987)
FLText-based; direct prohibition requiredCommon law impossibility applied narrowlyContractual terms enforcedOrder must prohibit — not merely burden — performance
ILStrict; pandemic must be explicitly listedImpracticability requires severe disruption; mitigation proof requiredStrict; cure periods rarely grantedAligned with NY approach; most COVID claims denied
PAStrict; foreseeability heavily weighted against claimantImpossibility standard; impracticability narrowly appliedContractual terms enforced; late notice = waiverPost-Feb 2020 pandemic claims face foreseeability bar
OHModerate; UCC § 2-615 for goodsImpracticability for goods under UCC; reasonable standard for servicesContractual terms generally enforcedGovernment actions recognized where enumerated
GAModerate; frustration more liberal than impossibilityFrustration of purpose viable alternative to impossibilityContractual terms enforcedFrustration doctrine applied more liberally than in NY
MIModerate; contract allocation examined firstImpracticability available; courts examine risk allocation at signingReasonable; strict waiver uncommonSupply chain disruptions given more favorable treatment
WAStrict; notice compliance emphasizedCommon law impossibility; impracticability applied narrowlyStrict; late notice = complete waiver in most casesStrongest notice-waiver jurisdiction; calendar deadlines carefully
COBalanced; UCC proportional fault for goodsImpracticability under UCC; government action recognizedContractual terms enforcedGovernment orders with explicit enumeration recognized
MAFlexible; "unreasonably burdensome" standardBroader impracticability standard than most statesReasonableness-based; courts may excuse minor delaysMost receptive to COVID gathering prohibition claims
NJMost receptive to COVID force majeure claimsImpossibility applied to defeat no-refund clauses; Facto v. PantagisContractual terms enforced; courts somewhat lenient on cureFacto v. Pantagis (App. Div. 2021); Hess Corp. (D.N.J. 2021)
VAStrict; near-total impossibility requiredFrustration rarely applied; impossibility standard dominantContractual terms strictly enforcedMost contractarian among non-DE states; text governs
MNModerate; Restatement § 261 for impracticabilityImpracticability available; contract risk allocation examined firstContractual terms enforcedSupply chain and government action FM recognized where listed

This table reflects general judicial approaches as of March 2026 based on publicly available court decisions. Results in specific cases depend on exact contract language, the factual record, and applicable statutory law.

Force Majeure Clause Review Checklist

12 items to evaluate in any force majeure provision before signing

ItemStatusWhat to Check
Event List CompletenessRequiredDoes the clause explicitly cover pandemics, epidemics, government orders, and supply chain disruptions? Post-COVID, these are essential inclusions.
Catch-All LanguageRequiredIs there catch-all language covering events not specifically enumerated ('and other events beyond the party's reasonable control')? Or is coverage limited strictly to the listed events?
Economic Events Carve-OutRequiredDoes the clause explicitly exclude pure economic events — inflation, commodity price changes, market downturns — from force majeure coverage?
MutualityRequiredDoes the clause protect both parties equally, or only one party? One-sided force majeure provisions are risk-shifting mechanisms, not genuine excuse doctrine.
Notice RequirementsRequiredIs there a specified notice timeline (5-10 business days is standard)? Content requirements? Consequences for late notice?
Causation StandardRequiredDoes the clause require the force majeure event to 'cause' the performance failure? 'Directly cause' is narrower than 'contribute to' — confirm which standard applies.
Mitigation ObligationRequiredIs the claiming party required to use commercially reasonable efforts to overcome the disruption and resume performance? Are there specific mitigation steps defined?
Suspension Period and ThresholdRequiredIs there a defined period after which performance must resume or the contract may be terminated? 60-180 days is the typical commercial range depending on contract type.
Termination RightsRequiredCan either party terminate if force majeure continues beyond the threshold? Is the termination right mutual, or available only to one party?
Payment Treatment During SuspensionRecommendedWhat happens to payment obligations during a force majeure suspension? Are fees suspended, deferred, or still owed for fixed commitments?
Governing State Anti-Impracticability RulesRecommendedDoes the governing state's law supplement or limit the contractual force majeure provision? Check for state-specific common law limitations — especially New York (Kel Kim) and Delaware.
Industry-Specific CoverageRecommendedDoes the clause address the industry-specific risks most relevant to your contract type — weather for construction, government orders for events, upstream supplier failures for supply chains?

Have a contract with a force majeure clause?

Upload it now and get an instant AI-powered review — red flags, missing protections, and negotiation suggestions for every clause, including force majeure. Just $4.99.

Check My Contract Free →

Frequently Asked Questions About Force Majeure

14 questions answered for freelancers and small businesses

1What does "force majeure" mean in a contract?

Force majeure (French for "superior force") is a contract clause that excuses one or both parties from their performance obligations when an extraordinary event beyond their control makes performance impossible, impracticable, or pointless. Common triggering events include natural disasters, pandemics, wars, government actions, labor strikes, and infrastructure failures. When a valid force majeure event occurs, the affected party's obligations are typically suspended for the duration — and if the event continues beyond a defined threshold, either party may have the right to terminate the contract without liability.

2Did COVID-19 qualify as force majeure?

It depended almost entirely on the specific language of each contract's force majeure clause. Pre-2020 contracts that listed only natural disasters, earthquakes, and floods generally did not protect parties from COVID-related disruptions, because courts refused to interpret "natural disaster" to include a pandemic. Contracts that explicitly included "pandemic," "epidemic," or "government orders" had a much stronger basis for invoking force majeure. The leading cases — JN Contemporary Art LLC v. Phillips Auctioneers (S.D.N.Y. 2021) and Hess Corp. v. Port Authority Trans-Hudson Corp. (D.N.J. 2021) — both found force majeure triggered where the clause explicitly covered government orders or epidemics.

3What was the holding in Kel Kim Corp. v. Central Markets and why does it matter?

Kel Kim Corp. v. Central Markets (N.Y. Ct. App. 1987) is the foundational force majeure precedent in New York — the most commercially active jurisdiction in the country. The New York Court of Appeals held that force majeure catch-all language must be interpreted ejusdem generis: constrained to events of the same type as those specifically enumerated in the clause. A tenant's difficulty obtaining liability insurance was not the same type of event as wars, acts of God, and government shutdowns. The practical impact is significant: in New York, you cannot rely on catch-all language to cover events not specifically enumerated. Every force majeure event you want protected in a New York-governed contract must be explicitly listed.

4What is the difference between force majeure and impossibility of performance?

Force majeure is a contractual provision — a clause the parties explicitly negotiated. It applies only to events listed in the clause (or covered by catch-all language) and provides the remedies specified in the contract. Impossibility of performance is a common law doctrine that can excuse performance without any contractual provision, but the bar is much higher: performance must be objectively impossible for anyone — not merely difficult or expensive for the claiming party. Facto v. Pantagis (N.J. App. Div. 2021) applied impossibility to excuse a COVID-19 wedding cancellation even when the venue had a no-refund clause, showing that the doctrine can override contract terms in extreme circumstances.

5What is the difference between force majeure and frustration of purpose?

Force majeure excuses performance when an extraordinary event makes performance impossible or impracticable. Frustration of purpose excuses performance when performance is still possible but the fundamental reason for entering the contract has been eliminated. Example: a company licenses a rooftop to watch a parade; the city cancels the parade due to a government order. The rooftop is still usable — performance is technically possible — but the entire purpose of the contract has been frustrated. Courts require near-total destruction of purpose; reduced value or profitability is not enough. Several COVID-19 cases succeeded on frustration of purpose grounds in New Jersey and California even where force majeure clauses were inadequate.

6What notice do I need to give to invoke force majeure?

The notice requirement is governed by your specific contract. Most commercial force majeure clauses require written notice within 5-10 business days of the occurrence of the force majeure event, specifying the nature of the event, its anticipated duration, and the steps being taken to mitigate. Failure to provide timely notice can waive your force majeure defense entirely — particularly in New York and Washington, where courts apply strict notice requirements. Always provide notice even if you are uncertain whether the event qualifies; you can withdraw a premature force majeure notice, but you cannot retroactively provide a late one.

7Am I still required to mitigate even if I invoke force majeure?

Yes — virtually every commercial force majeure clause imposes a mitigation obligation on the claiming party. Even when a genuine force majeure event has occurred, you are required to use commercially reasonable efforts to overcome or minimize the disruption and resume performance as quickly as practicable. This does not require extraordinary financial sacrifice — you are not expected to pay ten times the market rate for substitute components — but it does require genuine, demonstrable effort. In Phibro Energy, Inc. v. Empresa Nacional de Petroleo (2d Cir. 1991), the court required the seller to exhaust reasonable alternative shipping options before force majeure could be invoked for a dock fire disruption.

8Can I be terminated if force majeure lasts too long?

Yes, if your contract contains a duration threshold and termination provision — and most well-drafted commercial force majeure clauses do. The typical commercial threshold is 60-90 days for short-term agreements and 180 days for construction or long-term supply agreements. Once this threshold is reached, either party (or sometimes only the non-affected party) may terminate the contract without liability. If your force majeure clause does not include a termination threshold, you may be locked in indefinite suspension — a significant risk that should always be addressed at the drafting stage.

9Does force majeure excuse my payment obligation?

Whether force majeure excuses payment depends on which party is invoking it and what your contract says. When a vendor invokes force majeure to excuse delayed delivery, the client's obligation to pay for undelivered services or goods is typically suspended. When a client invokes force majeure to excuse inability to use services, payment treatment varies. COVID-19 generated extensive litigation over commercial lease rent obligations, with most courts — following traditional landlord-tenant doctrine — holding that tenants still owed rent because the landlord's obligation to provide the premises was technically performed. Always negotiate payment treatment during suspension explicitly rather than relying on implied rules.

10What if my supplier has a force majeure event — does that protect me?

Whether your supplier's force majeure event protects you under your downstream contracts depends on whether your force majeure clause covers upstream supply chain disruptions. Many traditional force majeure clauses protect you only for events that directly affect your operations — they do not automatically extend to events at your suppliers. Post-COVID, many supply agreements now explicitly include 'inability of suppliers to deliver materials, components, or services due to force majeure events affecting such suppliers.' If your force majeure clause does not address upstream cascades, you may be excused from liability to your supplier but still liable to your customers — a gap that needs to be addressed at the drafting stage.

11What happens if my contract has no force majeure clause?

Without a force majeure clause, your performance obligations are governed by default common law rules. The available common law doctrines are: impossibility (performance must be objectively impossible for everyone); commercial impracticability under UCC § 2-615 (an extraordinary contingency makes performance impracticable, not merely more expensive — requires a basic assumption failure); and frustration of purpose (the entire basis for the contract has been eliminated). These doctrines are difficult to invoke and have narrow requirements. If a significant disruption occurs under a contract with no force majeure clause, consult an attorney immediately to evaluate which common law arguments are available under the governing state's law.

12Can a vendor use force majeure to raise prices?

Generally no — force majeure excuses delay or non-performance, not repricing. A legitimate force majeure clause provides relief from obligations that cannot be performed; it does not grant the right to change the pricing terms. However, some aggressively drafted vendor force majeure clauses explicitly include a right to 'adjust pricing' during force majeure events. Gulf Oil Corp. v. Federal Energy Regulatory Commission (5th Cir. 1983) established that commodity price spikes are foreseeable commercial risks that do not qualify as force majeure or impracticability. If you see a force majeure clause that grants a unilateral price adjustment right, treat it as a red flag requiring negotiation.

13How do AIA construction contracts handle force majeure?

The AIA A201 General Conditions § 8.3.1 is the dominant construction force majeure standard. It grants schedule relief (extension of Contract Time) for force majeure events but does not automatically grant additional compensation for increased performance costs during the disruption. This is a critical gap for contractors facing supply chain disruptions — they may get more time but still face compressed margins on fixed-price contracts. Post-2020 AIA contract riders increasingly add supply chain disruption language and material cost escalation provisions alongside traditional force majeure schedule relief.

14What is the "act of God" clause and how does it differ from force majeure?

"Act of God" is an older term describing natural phenomena — earthquakes, floods, hurricanes, lightning, volcanic eruptions — that occur without human intervention. Modern force majeure clauses are broader: they include acts of God plus human-caused extraordinary events such as wars, terrorism, government actions, pandemics, labor strikes, and infrastructure failures. A contract that refers only to "acts of God" provides significantly narrower protection than a modern force majeure clause. Courts interpret "act of God" strictly to cover only natural phenomena; they will not stretch it to cover pandemics, government orders, or supply chain disruptions.

15How does business interruption insurance interact with force majeure clauses?

Force majeure clauses and business interruption (BI) insurance solve different problems. Force majeure clauses allocate contractual obligations between parties — they excuse performance. BI insurance provides financial compensation for business losses during disruptions. Neither substitutes for the other. COVID-19 revealed that pre-2020 BI policies, like pre-2020 force majeure clauses, largely failed to cover pandemic losses because both relied on implicit interpretations rather than explicit text. Post-COVID, specialized communicable disease endorsements and supply chain insurance products have emerged. A well-protected business has both: force majeure clauses in contracts and BI insurance that explicitly covers pandemic and government-order scenarios.

Ready to review your contract?

Upload any contract and get a plain-English AI analysis with red flags, missing protections, and negotiation suggestions — including your force majeure clause.

Check My Contract Free →

Not legal advice. For educational purposes only.